You are working on a software development project. The sponsor wants to make a change to the Scope after it has been baselined. You want to know the procedure that how to manage these changes. What is the BEST place to look for this information?
WBS Scope management plan Change management plan Business Case
As per yours answers Scope management plan is right but according me see page 169 pmbok6 change management plan is right if question says how is controlled then scope management plan is right
pl correct me if I m wrong
|
|
|
|