                You are working on a software development project. The sponsor wants to make a change to the Scope after it has been baselined. You want to know the procedure that how to manage these changes. What is the BEST place to look for this information?
 WBS
 Scope management plan
 Change management plan
 Business Case
 
 As per yours answers Scope management plan is right but according me see page 169 pmbok6 change management plan is right
 if question says how is controlled then scope management plan is right
 
 
 pl correct me if I m wrong
 
 
 | 
    | 
             | 
            
         | 
    |  | 
            
        
    
                           
    