Early start calculation
Rank: Newbie
Groups: Registered
Joined: 12-04-2020(UTC) Posts: 1
|
I was taking the assessment test from your portal for 'Schedule Management'. Question number 2 is to to calculate ES of activity E.
I start with '0' instead of '1'. Anyhow for me answer should be '5'. Although, there is no option of 5 in the given answers and also the solution given is not self explanatory. I really need help otherwise if I am calculation it wrong then I really need to understand this concept before moving forward.
Activity Precedent Weeks
Start None 0 A start 1 B start 3 C start 5 D A 9 E B,C 2 F C 3 G D 4 H E 8 I F 2 End G,H,I 0
Please do not ignore this message, I really need help.
For me, activity E has 2 predecessor activities (B, C). Early finish of B is 3 weeks and early finish of C is 5 weeks so Early start of E is 5 weeks. Please explain.
|
|
|
|
Rank: Administration
Groups: Administrators
Joined: 24-12-2014(UTC) Posts: 15
|
Hi Sarbjot, your course related queries should be put in either the course specific forum or the general forum used by the course provider. Your course provider, Izen has a specific forum to address such queries. Please visit the forum in izenbridge.com site.
|
|
|
|
Quampus Forum
»
Q-Learn
»
Q-Live
»
Early start calculation
Forum Jump
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.